Development of a solar park

One example of the development of a solar park under the project management of Energietechnik Pegasus is the community of Gerwisch. Once you click them, the pictures will be zoomed in and explained in more detail.

  • Power output: 8.625 megawatt
  • Construction time: 16 weeks


Components:

  • substructure of the framework by ramming
  • preinstallation of the framework
  • installation of the modules
  • erecting of the boards
  • cabling of the boards
  • cabling of the interior park
  • inverter installation
  • connecting to local line

 

substructure of the framework by laser and GPS-guided ramming preinstallation of the framework installation of the modules FS 275 First Solar erecting of the boards cabling of the boards cabling details cabling details cabling and grounding of the boards inverter installation inverter Sputnik Solar Max 300C before connection with the grid aerial photograph of the site in its almost completed stage